Edit the shifts of a resource

Example: Due to a reduced demand for a product, the night shift must not run production on certain resources for the coming month.

  1. Choose Production Management > Planning Cells in the Navigation Pane.
  2. Select the planning cell.
  3. Choose the tab Planning.
    To edit the shifts for 1 resource, right-click the resource, choose Edit Shifts in the shortcut menu and proceed with step 8.
  4. Click Edit Shifts .
  5. Check the machines or work centers for which the days need to be edited. Where applicable, use the buttons Check All , Uncheck All , Check Selection , Uncheck Selection .
  6. Click Next.
  7. In the option group Period in the field From, check the start of the period for which the shifts must be edited, and select in the field Until the end of the period for which the shifts must be edited.
  8. In the option group Day, enter the day or click Day Selection , select the day and click Finish.
    With this you select in which day regime the shifts must be edited.
  9. Do one of the following:
    • Check the shifts that need to be productive.
    • Uncheck the shifts that need to be unproductive.
    If you are not working with CRP, you can enter the required resources (employees) in the column Resource Availability.
  10. Click Finish.
    A summary of the modifications is displayed.
  11. Click Finish.