Copy an offline planning

To be able to test several optimization scenarios, the offline planning can be copied. After having determined the most optimal planning, this can be put back online.
  1. Choose Production Management > Planning Cells in the Navigation Pane.
  2. Select the planning cell.
  3. Choose the tab Planning.
  4. Click Edit Planning .
  5. Click Copy Planning .
    The planning is copied and will appear in the list with a new sequence number as suffix.
  6. The copied planning is not editable by default. To make it editable, click Set Editable in the toolbar.
    Only one planning in the list can be editable at the same time.
  7. To remove a copy of the planning, select the copy in the list and click Remove Planning in the toolbar.